Friday, 28 June 2013

This week the Facing Brickwork has commenced with the use of Wellford Buff bricks.
 

Friday, 21 June 2013

The first 4 plots are now complete with timber frame and roof coverings. The brickwork face will shortly commence.
 


If there is a local spokesperson for the Sheepridge area, could they please contact Gary Wilson, the Site Manager on 01484 517391. He would like to keep all the local residents informed of future works and upcoming events. There will also be regular letter drops with information regards the project.

Monday, 3 June 2013

The first timber frame plots have commenced with the use of a 50ton crane. Can we please remind parents to inform their children not to gain access to site and that site is CCTV monitored.