With the foundation and private drainage works complete to 3 of the 4 blocks, the substructure brickwork is underway with Block 1 virtually complete. Once the substructure brickwork is in place, the beam and block floor can then be installed.
Thursday, 18 April 2013
Tuesday, 9 April 2013
Site has made good progress this week, although only a short week, the foundations to 3 of the 4 blocks have progressed well. The sub-structure block work is still due to start next week whilst the foundations will continue. Drainage and ducting to the underside of the blocks will also be available for the ground worker to start over the coming days.
Wednesday, 3 April 2013
A slow week at on site this week due to the recent heavy snow.
Unfortunately, due to the depth of the snow the ground workers were unable to get to site for the first couple of days, and then they were unable to carry out any productive work for the last couple of days before the Easter break.
With improved weather due after Easter, progress should be made with the continuation of the foundations ahead of the bricklayers starting with the work to the underside of the foundations.
A frustrating week, for the first one of Spring…..!