Wednesday, 3 April 2013

A slow week at on site this week due to the recent heavy snow.

Unfortunately, due to the depth of the snow the ground workers were unable to get to site for the first couple of days, and then they were unable to carry out any productive work for the last couple of days before the Easter break.

With improved weather due after Easter, progress should be made with the continuation of the foundations ahead of the bricklayers starting with the work to the underside of the foundations.

A frustrating week, for the first one of Spring…..!