Monday, 4 March 2013

The large trees at the front of the site have gone and the land has now been cleared and stoned-up ready for excavating the foundations. The site cabins are due on site this week with temporary power and electricity to them to follow. Over the next couple of weeks the ground-workers will be starting digging out for the foundations and the drainage to the plots. The outline of the blocks will soon become evident as the foundations are concreted.